RTP DesportoMarco Silva alerta para Gil Vicente com qualidade para criar problemasESPN Deportes¿Cómo le fue a Checo Pérez en la qualy del GP de España?Punch54 countries offering eVisa to NigeriansThe Jerusalem PostIran used Chinese-sourced satellite images to target US bases, intelligence reveals - reportESPNWeek 2 preview: Ohio State-Texas leads SEC-Big Ten showdowns, plus five huge Big 12 gamesוואלהארבעה פצועים בתאונת דרכים בכביש 89, בהם בת 63 במצב בינוניBollywood HungamaBIG DEVELOPMENT: PVR INOX proposes to SCRAP VPF for all films; move comes a year after Jolly LLB 3 controversy; Saiyaara, War 2 ‘sunset clause’ revelationsFootball ItaliaSpalletti: ‘Juventus must end alibi mentality’ around injury crisisBusiness AMRussische marineschepen zorgen voor verhoogde alertheid bij passage in de Middellandse ZeeIl Fatto QuotidianoUfo, dal primo recupero di oggetto volante non identificato fatto al mondo agli avvistamenti di San Cesareo e Treviso: su Focus il programma che indaga i misteri extraterrestiRMF2488-latka w nocy wypadła z okna szpitala w Koninie. Nie żyjeRapplerLIVE UPDATES: First BARMM parliamentary elections
The Daily Newsstand · Free, Always
Saturday, September 12, 2026

Quality concerns prompt further tests on concrete used in 3 public housing blocks

Translate

The quality of concrete used in three blocks of a public housing estate under construction in Tung Chung requires further testing and review, Hong Kong’s Housing Authority has revealed.

According to official documents, the main contractor on the project is Able Engineering. The same company is also involved in a scandal over defective lift installation work at an expansion project at Queen Mary Hospital in Pok Fu Lam.

The authority said on Saturday that regular checks had uncovered issues with the quality of concrete used in three blocks of the estate at Tung Chung Area 42 on Lantau Island between late August and early September.

“The Housing Authority’s engineering team discovered during routine concrete cube strength tests between late August and early September that the quality of concrete used in certain structural components of blocks 3, 4 and 5 at the Tung Chung Area 42 public housing estate required further review and testing,” a spokesman said.

The estate, with a total site area of about four hectares, comprises six residential blocks, providing more than 6,000 public housing flats for a planned population of 16,611. The project’s cost was estimated at about HK$5.4 billion in 2023.

The authority said it had instructed the contractor to extract additional concrete core samples for compressive strength testing in accordance with contract standards to assess whether the concrete strength met the design and contractual requirements.