Daily MaverickTHE INTERVIEW: We asked Trevor Noah what makes SA comedy special — here’s what he saidPunchImplement Ogun disability law, PWDs beg AbiodunESPNLongtime Lakers P.A. announcer Tanter diesESPN DeportesGabriela Martínez: lloré tras debutar en el juego del Big TenThe Jerusalem PostBoy George stands with Israel, so where are the rest of the world's artists? - editorialSözcüSON DAKİKA... Ümit Boyner'in oğlu Sinan Bolak gözaltına alındıCNN TürkHava Durumu (24-09-2026)Sky TG24Terra Madre Salone del Gusto 2026: 40 anni di Slow Food ItaliaDigital Spy17 huge Coronation Street spoilers for next week (28 September to 2 October)3DNewsHUAWEI nova 16s Pro: флагманская камера в теле смартфона среднего классаBusiness AMWat is de Russische schaduwvloot en hoe helpt die om sancties te omzeilen?VarietyAsia Video Content Spend to Hit $15 Billion in 2026 as Streaming and Local Film Draw Capital, Media Partners Asia Report Finds
The Daily Newsstand · Free, Always
Thursday, September 24, 2026

Metro Manila subway project marks first tunnel boring breakthrough

Translate
SEE YOU ON THE OTHER SIDE President Marcos visits on Wednesday the future Quezon Avenue station of the Metro Manila Subway project, where workers have achieved their first tunnel boring machine breakthrough. It marked the completion ofexcavation works between this station and the southbound portion of North Avenue station, which is located 1.1 kilometers away. —Marianne Bermudez

MANILA, Philippines — President Marcos on Wednesday called the first tunnel boring machine (TBM) breakthrough of the Metro Manila Subway Project (MMSP) at Quezon Avenue station an important milestone in the construction of the country’s first-ever underground railway system.

Marcos inspected the site of the Quezon Avenue station, where excavation has been completed up to the southbound portion of North Avenue station—a distance of about 1.1 kilometers (km) and 34 meters below ground.

A breakthrough refers to the process in which a TBM breaks thorough the final wall after completing the tunnel excavation process.

Article continues after this advertisement

Tunnel boring operations are currently continuing from Quezon Avenue station toward East Avenue station. The two are 1.5 km apart.

FEATURED STORIES

NEWSINFO

NEWSINFO

NEWSINFO

READ: JV Ejercito: No more delays in NSCR, Metro Manila subway

“Little by little, we can see that our subway project is gradually taking shape. We can see it coming together,” the President told reporters.

“Once this is completed, the people living here will be very fortunate because they will have a subway, they will have the MRT (Metro Rail Transit). They will have many ways to get around the metro,” he said.

The two underground stations and their connecting tunnels are part of MMSP’s Contract Package 102, awarded to the joint venture of Japanese firm Nishimatsu Construction Co. Ltd. and local construction company D.M. Consunji Inc. in 2022.

Article continues after this advertisement

Construction of the Quezon Avenue and East Avenue stations began on May 10, 2023.

President Marcos last week led the groundbreaking ceremony of the MMSP’s Ninoy Aquino International Airport (Naia) Terminal 3 station in Pasay City, where he said the subway project was 60 percent complete.

Article continues after this advertisement

The P488.48-billion MMSP, financed through loans from the Japan International Cooperation Agency, is part of ongoing efforts to modernize the country’s railway system and improve connectivity across Metro Manila.

Faster travel

The government aims to complete construction of the 33-km, 17-station underground railway system by the last quarter of 2031.

The subway will stretch from East Valenzuela to Bicutan in Taguig City, providing a faster and more reliable mass transportation option across Metro Manila.

Your subscription could not be saved. Please try again.

Your subscription has been successful.

Once fully operational, the MMSP is expected to reduce travel time from Valenzuela City to Naia from about 1.5 hours to 41 minutes. /cb